South Bridge Project Delayed? PDF Print E-mail
Written by Sharon Vanhouwe   
Monday, 01 October 2012 14:13

bridge south bridge construction site

The Circle Drive South Project remains under construction as long as weather will allow.

 

Despite a sunny and dry September, wet weather and ground conditions from May and June have significantly offset the construction schedule.

 

All the City is saying at this point is they will continue to review the options with respect to getting the project open this fall, but any decision will be made from a safety and practicality standpoint.

 

The City wants to make sure that any opening does not have a detrimental effect on public safety; nor does the City want to create additional delays in getting the project ultimately completed.

One of the big questions on the minds of taxpayers these days is the daily penalties the City can impose on the contractor for being late with the project.

 

The City can levy a charge of ten thousand dollars for every day the project is late, but at this point, city manager, Murray Totland is saying, the City has not had those discussions with Graham Flatiron yet.

 

And, he says contractual details are not subject to public discussion or disclosure.